Tentative Production schedule
Tentative Production Schedule of PCCW – Mobile ‘MTR’ TVC
(Rev. 1 – 29 Mar. 07)
30/03/2007 (Fri) am Director and Team travel to Hong Kong
12.00 Director arrive in Hong Kong Airport Int. Pre Production Meeting with Production House
14:30 Pre-Production Meeting with Client
01/04007 (Sun) Agency & Client fly to Bangkok for final check
02/04/2007 (Mon) Pre-light at Sky Exits Studio
03/04/2007 (Tue) Studio Shoot
04/04/2007 (Wed) Print shoot
05/04/2007 (Thu) Agency to preview rough cut
Guide Track recording in HK
06/04/2007 (Fri) Present rough cut to Client for approval
08/04/2007 (Sun) Client & 1 x Agency personnel return to HK
09/04/2007 (Mon) Client to present Rough cut to management in HK
Contingency for rough cut revision (If necessary)
10/04/2007 (Tue) Rev. rough cut to Client’s management
Music Score
11/04/2007 (Wed) On-line for compositing & supertitling
12/04/2007 (Thu) am Agency fly back to Hong Kong
13/04/2007 (Fri) VO recording & mixing in HK
Present final TVC to Client for approval
16/04/2007 (Mon) Airdate
(Rev. 1 – 29 Mar. 07)
30/03/2007 (Fri) am Director and Team travel to Hong Kong
12.00 Director arrive in Hong Kong Airport Int. Pre Production Meeting with Production House
14:30 Pre-Production Meeting with Client
01/04007 (Sun) Agency & Client fly to Bangkok for final check
02/04/2007 (Mon) Pre-light at Sky Exits Studio
03/04/2007 (Tue) Studio Shoot
04/04/2007 (Wed) Print shoot
05/04/2007 (Thu) Agency to preview rough cut
Guide Track recording in HK
06/04/2007 (Fri) Present rough cut to Client for approval
08/04/2007 (Sun) Client & 1 x Agency personnel return to HK
09/04/2007 (Mon) Client to present Rough cut to management in HK
Contingency for rough cut revision (If necessary)
10/04/2007 (Tue) Rev. rough cut to Client’s management
Music Score
11/04/2007 (Wed) On-line for compositing & supertitling
12/04/2007 (Thu) am Agency fly back to Hong Kong
13/04/2007 (Fri) VO recording & mixing in HK
Present final TVC to Client for approval
16/04/2007 (Mon) Airdate